The Housing Operating Model 2026

CASE STUDY

THE PROJECT BEGINS WITH STRONG ALIGNMENT Through a prior government land release and funding program, the State Government and a community housing provider (CHP) were working towards the shared objective of delivering social and affordable housing, with grant funding and concessional finance also available to support delivery. On paper, the ingredients appeared to be in place, including public land, an identified housing need, a capable delivery partner and a funding program actively seeking viable CHP-led projects. A GOVERNMENT AND COMMUNITY HOUSING PROVIDER COLLABORATION

THE FIRST CONSTRAINT WAS LAND Although it was being released for a social and affordable housing purpose, government policy required it to be sold at market value, which is a standard process across many Governments (with varying flexibility across the nation). The site comprised small townhouse lots on constrained, sloping land, and the full market-value land cost remained despite the below-market housing outcome being sought. A discounted land contribution, deferred payment or other value-sharing mechanism may have supported viability at the outset. Instead, the CHP had to solve for the full land cost within an already tightly constrained project feasibility. THE CHP’S RESPONSE The CHP proposed amalgamating the separately titled lots and revising the built form to increase yield, including townhouses and a low-rise apartment component. The higher-yield scheme was designed to absorb the high land price, improve value for money and keep the social and affordable housing project viable.

THE CUMULATIVE IMPACT In this case, one part of government was calling for viable CHP-led projects, while the combined effect of land and planning settings elsewhere prevented this project from proceeding. Government had land and funding available, but the land- pricing policy embedded a viability gap. When the CHP developed a higher-yield response to overcome that gap, a separate planning position prevented the solution from progressing. Each decision could be explained within its own mandate, yet together, produced the opposite of the whole- of-government objective. This resulted in no project, no drawdown of the available funding and no additional social or affordable homes. Similar challenges can be observed across many housing projects, where authority requirements, utility interfaces, environmental and heritage considerations, planning processes and multiple approval points can collectively create a risk environment that undermines project feasibility and, ultimately, prevents projects from progressing. Major infrastructure projects often address this by bringing these issues together under a single governance and delivery framework, sometimes supported by project-specific legislation, to resolve interdependencies concurrently rather than sequentially.

THE SECOND CONSTRAINT WAS PLANNING

The second constraint emerged when the CHP sought the planning support required to demonstrate funding readiness. The revised scheme did not align with the original planning intent for the site, so planning support was not provided. Without that support, the project could not satisfy the grant program’s requirements and was ultimately not funded.

5