The Industrial Land Shift

NATIONAL OVERVIEW

SYDNEY

MELBOURNE

BRISBANE

PERTH

ADELAIDE

CONTACT INFORMATION

THE INDUSTRIAL LAND SHIFT

| 12

Development Lead Times Vary Significantly

The timeframe required to bring industrial land to market differs materially by state and is influenced by planning approvals, infrastructure delivery, utility availability and servicing requirements. While planning approvals are an important milestone, the provision of roads, power, water, sewer and telecommunications infrastructure often determines when land can be developed. As a result, the volume of zoned industrial land does not necessarily reflect the amount of

ZONED & SERVICED (Indicative time for delivery)

ZONED & UNSERVICED (Indicative time for delivery)

UNZONED & UNSERVICED (Indicative time for delivery)

STATE

1.5 – 2.5 years Development application, development consent, construction certificate and construction of facility

3 - 6 years Infrastructure servicing, subdivision (where required), development consent, construction certificate and construction of facility

6 - 10 years Rezoning, precinct planning,

NEW SOUTH WALES

infrastructure delivery, subdivision, development consent, construction certificate and construction of facility

1.5 – 2.0 years Planning permit, building permit and construction of facility

2 - 4 years Subdivision permit, infrastructure servicing, Statement of Compliance, building permit and construction of facility

4 - 8 years Planning Scheme Amendment, Precinct Structure Plan, subdivision, infrastructure servicing, Statement of Compliance, building permit and construction of facility 5 - 7 years Planning scheme amendment, structure planning, Reconfiguring a Lot approval, operational works approval, infrastructure delivery, utility connections and construction of facility

VICTORIA

1.5 – 2.0 years Development approval, operational works approval (where required) and construction of facility

3 - 4 years Reconfiguring a Lot approval, operational works approval, infrastructure servicing, utility connections and construction of facility

land that is available for immediate development.

QUEENSLAND

1.5 – 2.0 years Development approval, building permit and construction of facility

2 - 3 years Subdivision approval, servicing works, clearance of conditions, building permit and construction of facility

4 – 7+ years Scheme amendment/rezoning,

subdivision approval, servicing works, clearance of conditions, building permit and construction of facility

WESTERN AUSTRALIA

1.5 – 2.0 years Planning consent, building consent and construction of facility

2 - 3 years Land division consent, infrastructure servicing, planning consent, building consent and construction of facility

4 – 7+ years Code Amendment, land division consent, infrastructure servicing, planning consent, building consent and construction of facility

SOUTH AUSTRALIA